Sandblasting
The user of this data is assumed to have a manufacturing background with the need to know all of the details of this model.

User Input
1. Enter the "Surface Area of Part".
The part shape can be round, square or irregular within reason.
2. The "Table Size (Diameter)" is defaulted to 8 feet.
The user can change if desired.
3. The "Cycle Time" for sandblasting is defaulted to 8 minutes.
The user can change.
4. The "% Table Utilized" is defaulted to 50 percent. User can change.
5. The "number of Pieces/Load" is calculated.
6. The final "Time per Piece" is the time to sandblast each part based on the criteria above.
Time per piece is based on 50% usage of the table.
Method provided by MTI Customer.